# Purchase Requisition Approval - User Guide
|
|
|
|
## Document Information
|
|
- **Document Type**: User Guide
|
|
- **Audience**: Procurement Staff, Department Heads, Finance Controllers
|
|
- **Last Updated**: 2025-10-30
|
|
- **Version**: 1.0
|
|
|
|
---
|
|
|
|
## Overview
|
|
|
|
This guide explains how to create, submit, and approve Purchase Requisitions (PRs) in the PIAM system. Understanding the approval workflow and document immutability rules is essential for efficient procurement operations.
|
|
|
|
---
|
|
|
|
## Table of Contents
|
|
|
|
1. [Purchase Requisition Lifecycle](#purchase-requisition-lifecycle)
|
|
2. [Creating a Purchase Requisition](#creating-a-purchase-requisition)
|
|
3. [Submitting for Approval](#submitting-for-approval)
|
|
4. [Approval Process](#approval-process)
|
|
5. [Document Immutability Rules](#document-immutability-rules)
|
|
6. [What You Can and Cannot Do](#what-you-can-and-cannot-do)
|
|
7. [Common Scenarios](#common-scenarios)
|
|
8. [Troubleshooting](#troubleshooting)
|
|
|
|
---
|
|
|
|
## Purchase Requisition Lifecycle
|
|
|
|
A Purchase Requisition moves through several statuses:
|
|
|
|
```
|
|
Draft → Pending Approval → Approved → Converted to RFQ/PO → Closed
|
|
↑ ↓
|
|
└────(rejected)
|
|
```
|
|
|
|
### Status Descriptions
|
|
|
|
| Status | Description | Can Edit? | Can Approve? |
|
|
|--------|-------------|-----------|--------------|
|
|
| **Draft** | Initial state, not yet submitted | ✅ Yes | ❌ No |
|
|
| **Pending Approval** | Submitted and awaiting approval | ❌ No | ✅ Yes |
|
|
| **Approved** | Approved and ready for procurement | ❌ No | ❌ No |
|
|
| **Rejected** | Rejected by approver, returns to Draft | ✅ Yes | ❌ No |
|
|
| **Converted to RFQ** | Converted to Request for Quotation | ❌ No | ❌ No |
|
|
| **Converted to PO** | Converted to Purchase Order | ❌ No | ❌ No |
|
|
| **Closed** | Completed or cancelled | ❌ No | ❌ No |
|
|
|
|
---
|
|
|
|
## Creating a Purchase Requisition
|
|
|
|
### Step 1: Access the PR Form
|
|
|
|
1. Navigate to **Procurement → Purchase Requisitions**
|
|
2. Click **"Create New Requisition"** button
|
|
3. The system creates a new PR in **Draft** status
|
|
|
|
### Step 2: Fill in Required Information
|
|
|
|
#### General Information
|
|
- **Requisition Number**: Auto-generated by system
|
|
- **Department**: Select your department from dropdown
|
|
- **Requested Date**: Date when items are needed
|
|
- **Purpose**: Describe why these items are needed
|
|
- **Priority**: Select urgency level
|
|
|
|
#### Budget Information
|
|
- **Budget Code**: Select the budget to charge
|
|
- **Company Code**: Select company/entity
|
|
- **Cost Center**: Select appropriate cost center
|
|
|
|
#### Line Items
|
|
For each item you need:
|
|
1. Click **"Add Item"**
|
|
2. Search and select the item
|
|
3. Enter **Quantity** and **Unit**
|
|
4. Enter **Unit Price** (if known)
|
|
5. Add **Remarks** if needed
|
|
|
|
### Step 3: Save Your Work
|
|
|
|
- Click **"Save Draft"** to save without submitting
|
|
- You can return later to continue editing
|
|
- Draft PRs remain editable until submitted
|
|
|
|
---
|
|
|
|
## Submitting for Approval
|
|
|
|
### When to Submit
|
|
|
|
Submit your PR when:
|
|
- All required information is complete
|
|
- Line items are accurate
|
|
- Budget information is correct
|
|
- You're ready for approval
|
|
|
|
### How to Submit
|
|
|
|
1. Review all information carefully
|
|
2. Click **"Submit for Approval"**
|
|
3. Confirm submission in the dialog
|
|
4. PR status changes to **"Pending Approval"**
|
|
|
|
### What Happens After Submission
|
|
|
|
Once submitted:
|
|
- ❌ **You cannot edit the PR anymore**
|
|
- ✅ Approvers receive notification
|
|
- ✅ PR enters the approval workflow
|
|
- ✅ You can view PR status anytime
|
|
|
|
### Important Notes
|
|
|
|
- Double-check all details before submitting
|
|
- Once submitted, you cannot make changes
|
|
- If rejected, PR returns to Draft for corrections
|
|
- Keep track of your PR number for reference
|
|
|
|
---
|
|
|
|
## Approval Process
|
|
|
|
### Who Can Approve?
|
|
|
|
Approvers are typically:
|
|
- **Department Heads**: For departmental purchases
|
|
- **Finance Controllers**: For budget approval
|
|
- **Procurement Managers**: For procurement approval
|
|
|
|
*Note: Your organization's approval hierarchy may vary*
|
|
|
|
### How to Approve a PR
|
|
|
|
1. Navigate to **Procurement → Purchase Requisitions**
|
|
2. Filter by **"Pending Approval"** status
|
|
3. Click on the PR to review
|
|
4. Review all details carefully:
|
|
- Items requested
|
|
- Quantities and prices
|
|
- Budget information
|
|
- Purpose and justification
|
|
5. Click **"Approve"** button
|
|
6. Add approval remarks (optional)
|
|
7. Confirm approval
|
|
|
|
### How to Reject a PR
|
|
|
|
If corrections are needed:
|
|
1. Click **"Reject"** button
|
|
2. **Add rejection reason** (required)
|
|
3. Confirm rejection
|
|
4. PR returns to Draft status
|
|
5. Requester can make corrections and resubmit
|
|
|
|
---
|
|
|
|
## Document Immutability Rules
|
|
|
|
### Why Are Approved PRs Locked?
|
|
|
|
Once a PR is approved:
|
|
- **Financial Control**: Budget is committed
|
|
- **Audit Compliance**: Approved amounts must be traceable
|
|
- **Process Integrity**: Prevents unauthorized changes
|
|
- **Procurement Accuracy**: What was approved is what gets procured
|
|
|
|
### Visual Indicators
|
|
|
|
When viewing a locked PR, you'll see:
|
|
- 🔒 **Lock icon** in the header
|
|
- **"Document Locked"** banner at the top
|
|
- **"View Only"** badge
|
|
- All fields are grayed out/disabled
|
|
- No Save or Submit buttons
|
|
|
|
### What Statuses Are Locked?
|
|
|
|
| Status | Locked? | Reason |
|
|
|--------|---------|--------|
|
|
| Draft | ❌ No | Still being prepared |
|
|
| Pending Approval | ✅ Yes | In approval workflow |
|
|
| Approved | ✅ Yes | Budget committed |
|
|
| Rejected | ❌ No | Returned for correction |
|
|
| Converted to RFQ/PO | ✅ Yes | Already converted |
|
|
| Closed | ✅ Yes | Process complete |
|
|
|
|
---
|
|
|
|
## What You Can and Cannot Do
|
|
|
|
### ✅ What You CAN Do
|
|
|
|
**With Draft PRs:**
|
|
- Edit all fields and line items
|
|
- Add or remove items
|
|
- Change quantities and prices
|
|
- Update budget information
|
|
- Save changes anytime
|
|
- Delete the PR if not needed
|
|
|
|
**With Approved PRs:**
|
|
- View all information
|
|
- Print or export the PR
|
|
- Track conversion to RFQ/PO
|
|
- View approval history
|
|
- View audit logs
|
|
|
|
**With Rejected PRs:**
|
|
- Make requested corrections
|
|
- Update based on rejection remarks
|
|
- Resubmit for approval
|
|
|
|
### ❌ What You CANNOT Do
|
|
|
|
**With Approved PRs:**
|
|
- Edit any field
|
|
- Change line items
|
|
- Modify quantities or prices
|
|
- Change budget information
|
|
- Delete the PR
|
|
|
|
**With Pending Approval PRs:**
|
|
- Edit while waiting for approval
|
|
- Change submitted information
|
|
- Cancel submission (must be rejected)
|
|
|
|
---
|
|
|
|
## Common Scenarios
|
|
|
|
### Scenario 1: I Need to Change an Approved PR
|
|
|
|
**Problem**: You discovered an error after approval
|
|
|
|
**Solution**:
|
|
1. Contact your supervisor or procurement manager
|
|
2. Explain what needs to be changed
|
|
3. If the PR is not yet converted:
|
|
- Admin may be able to help
|
|
- May need to create a new PR
|
|
4. If already converted to RFQ/PO:
|
|
- Changes must be made in RFQ/PO document
|
|
- Original PR remains unchanged for audit
|
|
|
|
**Best Practice**: Always double-check before submitting!
|
|
|
|
### Scenario 2: My PR Was Rejected
|
|
|
|
**Problem**: Your PR status shows "Rejected"
|
|
|
|
**Solution**:
|
|
1. Open the PR to view rejection remarks
|
|
2. Review what needs to be corrected
|
|
3. Make the necessary changes
|
|
4. Resubmit for approval
|
|
5. The PR will go through approval again
|
|
|
|
### Scenario 3: I Submitted the Wrong PR
|
|
|
|
**Problem**: You accidentally submitted a PR that's not ready
|
|
|
|
**Solution**:
|
|
1. Contact the approver immediately
|
|
2. Ask them to reject the PR
|
|
3. Add a note explaining it was submitted early
|
|
4. Make corrections when it returns to Draft
|
|
5. Resubmit when ready
|
|
|
|
### Scenario 4: I Can't Edit My Draft PR
|
|
|
|
**Problem**: The form shows "View Only" even though status is Draft
|
|
|
|
**Possible Causes**:
|
|
1. You're viewing the PR, not editing it
|
|
- Solution: Click "Edit" button
|
|
2. You're on the list view or detail view
|
|
- Solution: Navigate to edit page
|
|
3. Browser cache issue
|
|
- Solution: Refresh the page (Ctrl+F5)
|
|
|
|
### Scenario 5: System Shows "Document Locked" Error
|
|
|
|
**Problem**: You see an error message about document being locked
|
|
|
|
**What It Means**:
|
|
- The PR status doesn't allow editing
|
|
- This is a security feature to protect approved documents
|
|
|
|
**Solution**:
|
|
- If PR is Pending Approval: Wait for approval/rejection
|
|
- If PR is Approved: Cannot edit (see Scenario 1)
|
|
- If you believe this is an error: Contact system administrator
|
|
|
|
---
|
|
|
|
## Troubleshooting
|
|
|
|
### Error Messages
|
|
|
|
#### "Cannot modify purchase requisition in '[Status]' status"
|
|
- **Meaning**: PR is locked due to its status
|
|
- **Solution**: Check PR status; only Draft PRs can be edited
|
|
|
|
#### "This document is locked and cannot be edited"
|
|
- **Meaning**: PR has been approved or is beyond approval
|
|
- **Solution**: See [Scenario 1](#scenario-1-i-need-to-change-an-approved-pr)
|
|
|
|
#### "Purchase requisition not found"
|
|
- **Meaning**: PR may have been deleted or ID is incorrect
|
|
- **Solution**: Check PR number and try again
|
|
|
|
### Common Issues
|
|
|
|
#### Save Button Not Appearing
|
|
- **Check**: Is PR in Draft status?
|
|
- **Check**: Are you on the edit page (URL contains `/edit`)?
|
|
- **Check**: Do you have permission to edit?
|
|
|
|
#### Cannot Submit for Approval
|
|
- **Check**: Are all required fields filled?
|
|
- **Check**: Are there validation errors?
|
|
- **Check**: Is at least one line item added?
|
|
- **Check**: Is budget code valid?
|
|
|
|
#### PR Disappeared from List
|
|
- **Check**: Filter settings (status, date range)
|
|
- **Check**: Search for PR number directly
|
|
- **Check**: PR may have been deleted (if it was Draft)
|
|
|
|
---
|
|
|
|
## Best Practices
|
|
|
|
### Before Creating a PR
|
|
|
|
1. ✅ Verify budget availability
|
|
2. ✅ Gather all item specifications
|
|
3. ✅ Check with department for requirements
|
|
4. ✅ Confirm requested delivery date
|
|
|
|
### Before Submitting
|
|
|
|
1. ✅ Review all line items carefully
|
|
2. ✅ Verify quantities and units
|
|
3. ✅ Double-check budget code
|
|
4. ✅ Ensure purpose is clear
|
|
5. ✅ Check all required fields are filled
|
|
6. ✅ Review total amount
|
|
|
|
### For Approvers
|
|
|
|
1. ✅ Review budget availability
|
|
2. ✅ Verify items are appropriate
|
|
3. ✅ Check quantities are reasonable
|
|
4. ✅ Ensure prices are acceptable
|
|
5. ✅ Provide clear rejection reasons
|
|
6. ✅ Approve promptly to avoid delays
|
|
|
|
---
|
|
|
|
## Getting Help
|
|
|
|
### Internal Support
|
|
|
|
- **Technical Issues**: Contact IT Support
|
|
- **Approval Questions**: Contact your supervisor
|
|
- **Budget Questions**: Contact Finance Department
|
|
- **Procurement Process**: Contact Procurement Department
|
|
|
|
### Documentation
|
|
|
|
- **System Administrator Guide**: For technical details
|
|
- **FAQ Document**: For common questions
|
|
- **Training Materials**: Available from IT Department
|
|
|
|
---
|
|
|
|
## Glossary
|
|
|
|
**Draft**: Initial status of a PR, allows editing
|
|
|
|
**Immutable**: Cannot be changed or modified
|
|
|
|
**Line Item**: A single item/material on the PR
|
|
|
|
**Pending Approval**: PR is submitted and awaiting approval
|
|
|
|
**Purchase Requisition (PR)**: Internal document requesting to purchase items
|
|
|
|
**Rejection Remarks**: Reason provided when PR is rejected
|
|
|
|
**Status**: Current state of the PR in its lifecycle
|
|
|
|
**Workflow**: Series of steps a PR goes through from creation to approval
|
|
|
|
---
|
|
|
|
## Appendix: Quick Reference
|
|
|
|
### Keyboard Shortcuts
|
|
|
|
| Shortcut | Action |
|
|
|----------|--------|
|
|
| Ctrl+S | Save Draft (on edit page) |
|
|
| Esc | Close dialog/cancel action |
|
|
|
|
### Status Color Codes
|
|
|
|
- **Gray**: Draft
|
|
- **Yellow/Amber**: Pending Approval
|
|
- **Green**: Approved
|
|
- **Red**: Rejected
|
|
- **Blue**: Converted/Closed
|
|
|
|
### Important Reminders
|
|
|
|
1. 📌 Only Draft PRs can be edited
|
|
2. 📌 Always review before submitting
|
|
3. 📌 Approved PRs are permanently locked
|
|
4. 📌 Save your work frequently
|
|
5. 📌 Keep PR numbers for reference
|
|
|
|
---
|
|
|
|
**Document End**
|
|
|
|
*For technical details and configuration, see System Administrator Guide*
|