# What Happens After Purchase Requisition Approval
|
|
|
|
## Document Information
|
|
- **Document Type**: Process Guide
|
|
- **Audience**: All Procurement Users
|
|
- **Last Updated**: 2025-10-30
|
|
- **Version**: 1.0
|
|
|
|
---
|
|
|
|
## Overview
|
|
|
|
Understanding what happens after a Purchase Requisition (PR) is approved is essential for planning your procurement activities. This document explains the approval consequences, status transitions, and document immutability rules.
|
|
|
|
---
|
|
|
|
## Table of Contents
|
|
|
|
1. [Immediate Effects of Approval](#immediate-effects-of-approval)
|
|
2. [Status Transitions After Approval](#status-transitions-after-approval)
|
|
3. [Document Immutability Explained](#document-immutability-explained)
|
|
4. [Budget Impact](#budget-impact)
|
|
5. [Next Steps in Procurement](#next-steps-in-procurement)
|
|
6. [Audit Trail](#audit-trail)
|
|
7. [Frequently Asked Questions](#frequently-asked-questions)
|
|
|
|
---
|
|
|
|
## Immediate Effects of Approval
|
|
|
|
When an approver clicks "Approve" on a Purchase Requisition, several things happen instantly:
|
|
|
|
### 1. Status Change
|
|
```
|
|
Pending Approval → Approved
|
|
```
|
|
|
|
### 2. Document Lock
|
|
- ❌ **All editing is disabled**
|
|
- ❌ Cannot modify any field
|
|
- ❌ Cannot add or remove line items
|
|
- ❌ Cannot change quantities or prices
|
|
- ❌ Cannot update budget information
|
|
|
|
### 3. Approval Information Recorded
|
|
The system captures:
|
|
- **Approved By**: Name of the approver
|
|
- **Approved At**: Date and time of approval (UTC)
|
|
- **Approval Remarks**: Any comments from approver
|
|
- **User Information**: IP address and system details
|
|
|
|
### 4. Budget Commitment
|
|
- Budget is marked as committed
|
|
- Amount is reserved against budget code
|
|
- Available budget is reduced
|
|
- Budget tracking is updated
|
|
|
|
### 5. Notifications Sent
|
|
- Requester receives approval notification
|
|
- Procurement team is notified
|
|
- Finance team may receive notification
|
|
- Next step assignees are alerted
|
|
|
|
### 6. Audit Log Entry
|
|
- Approval action is logged
|
|
- Full audit trail is maintained
|
|
- Timestamps are recorded
|
|
- User actions are tracked
|
|
|
|
---
|
|
|
|
## Status Transitions After Approval
|
|
|
|
Once approved, a PR can move through these statuses:
|
|
|
|
### Approved → Converted to RFQ
|
|
|
|
**When**: PR is converted to Request for Quotation
|
|
|
|
**Process**:
|
|
1. Procurement team reviews approved PR
|
|
2. Decision made to obtain quotations
|
|
3. RFQ is created from PR
|
|
4. PR status updates to "Converted to RFQ"
|
|
|
|
**Impact**:
|
|
- PR remains permanently locked
|
|
- RFQ process begins
|
|
- Suppliers will be invited to quote
|
|
- Original PR serves as audit reference
|
|
|
|
### Approved → Converted to Purchase Order
|
|
|
|
**When**: PR is directly converted to PO (without RFQ)
|
|
|
|
**Process**:
|
|
1. Supplier is already known
|
|
2. Pricing is pre-agreed
|
|
3. PO is created directly from PR
|
|
4. PR status updates to "Converted to PO"
|
|
|
|
**Common Scenarios**:
|
|
- Single source supplier
|
|
- Framework agreement purchases
|
|
- Emergency procurements
|
|
- Low-value purchases
|
|
|
|
**Impact**:
|
|
- PR remains permanently locked
|
|
- PO is issued to supplier
|
|
- Delivery process begins
|
|
- Original PR serves as audit reference
|
|
|
|
### Any Status → Closed
|
|
|
|
**When**: PR is closed for various reasons
|
|
|
|
**Reasons for Closing**:
|
|
- ✅ **Completed**: Full procurement cycle finished
|
|
- ❌ **Cancelled**: No longer needed
|
|
- ⏸️ **On Hold**: Temporarily suspended
|
|
- 🔄 **Superseded**: Replaced by new PR
|
|
|
|
**Impact**:
|
|
- PR is permanently archived
|
|
- No further actions possible
|
|
- Audit trail is preserved
|
|
- Cannot be reopened
|
|
|
|
---
|
|
|
|
## Document Immutability Explained
|
|
|
|
### What Is Immutability?
|
|
|
|
**Immutability** means a document cannot be changed or modified after a certain point. For Purchase Requisitions, this happens at approval.
|
|
|
|
### Why Is It Important?
|
|
|
|
#### 1. Financial Control
|
|
- **Before Approval**: Amount can change
|
|
- **After Approval**: Amount is fixed
|
|
- **Reason**: Budget commitment must be accurate
|
|
|
|
Example:
|
|
```
|
|
PR #12345
|
|
Draft: $5,000 → Changed to $6,000 ✅ (allowed)
|
|
Approved: $6,000 → Cannot change to $7,000 ❌ (blocked)
|
|
```
|
|
|
|
#### 2. Audit Compliance
|
|
- What was approved must match what was procured
|
|
- Audit trail must show original approved amounts
|
|
- No retroactive changes allowed
|
|
- Complete accountability maintained
|
|
|
|
#### 3. Process Integrity
|
|
- Prevents bypassing approval workflow
|
|
- Stops unauthorized changes
|
|
- Maintains approval authority
|
|
- Ensures proper governance
|
|
|
|
#### 4. Legal Protection
|
|
- Approved document is legal commitment
|
|
- Serves as contract basis
|
|
- Protects organization from disputes
|
|
- Ensures compliance with regulations
|
|
|
|
### Which Statuses Are Immutable?
|
|
|
|
| Status | Immutable? | Can View? | Can Edit? | Can Approve? |
|
|
|--------|-----------|-----------|-----------|--------------|
|
|
| Draft | ❌ No | ✅ Yes | ✅ Yes | ❌ No |
|
|
| Pending Approval | ✅ Yes | ✅ Yes | ❌ No | ✅ Yes |
|
|
| Approved | ✅ Yes | ✅ Yes | ❌ No | ❌ No |
|
|
| Rejected | ❌ No | ✅ Yes | ✅ Yes | ❌ No |
|
|
| Converted to RFQ | ✅ Yes | ✅ Yes | ❌ No | ❌ No |
|
|
| Converted to PO | ✅ Yes | ✅ Yes | ❌ No | ❌ No |
|
|
| Closed | ✅ Yes | ✅ Yes | ❌ No | ❌ No |
|
|
|
|
### Visual Indicators of Immutability
|
|
|
|
When you view an immutable PR, you'll see:
|
|
|
|
#### 1. Lock Icon 🔒
|
|
```
|
|
Purchase Requisition #PR-2025-001234 🔒
|
|
```
|
|
- Appears in page header
|
|
- Clearly indicates locked status
|
|
- Tooltip explains why locked
|
|
|
|
#### 2. Document Locked Banner
|
|
```
|
|
┌─────────────────────────────────────────────────┐
|
|
│ ⚠️ This document is locked and cannot be edited │
|
|
│ Purchase requisitions cannot be modified after │
|
|
│ approval. Contact your administrator if changes │
|
|
│ are needed. │
|
|
└─────────────────────────────────────────────────┘
|
|
```
|
|
|
|
#### 3. View Only Badge
|
|
```
|
|
[View Only]
|
|
```
|
|
- Appears near action buttons
|
|
- Replaces edit/save buttons
|
|
- Clear visual cue
|
|
|
|
#### 4. Grayed Out Fields
|
|
- All input fields are disabled
|
|
- Text is grayed out
|
|
- No cursor in fields
|
|
- Clear visual difference from editable form
|
|
|
|
#### 5. No Action Buttons
|
|
- No "Save Draft" button
|
|
- No "Submit for Approval" button
|
|
- Only "Close" or "Back" available
|
|
- Print/Export may be available
|
|
|
|
---
|
|
|
|
## Budget Impact
|
|
|
|
### At Approval Time
|
|
|
|
#### Budget Commitment
|
|
When PR is approved, the budget is committed:
|
|
|
|
```
|
|
Budget Code: OPEX-2025-IT-001
|
|
Available Budget Before: $50,000
|
|
PR Amount: $10,000
|
|
Available Budget After: $40,000
|
|
Committed Budget: $10,000
|
|
```
|
|
|
|
#### Budget Tracking
|
|
- Amount is tracked against budget code
|
|
- Remaining budget is calculated
|
|
- Future PRs check available budget
|
|
- Budget reports show commitments
|
|
|
|
#### Budget Period
|
|
- Commitment is for current fiscal period
|
|
- Crossing fiscal years may require special approval
|
|
- Budget may roll over or expire based on policy
|
|
|
|
### What If Budget Changes?
|
|
|
|
#### Scenario: Budget Increased After Approval
|
|
- Approved PR amount doesn't change
|
|
- Additional budget available for new PRs
|
|
- Original PR remains as approved
|
|
|
|
#### Scenario: Budget Cut After Approval
|
|
- Approved PRs are honored
|
|
- May affect future PRs
|
|
- Finance may review commitments
|
|
- Special approval may be needed
|
|
|
|
#### Scenario: Budget Reallocated
|
|
- Finance handles budget transfers
|
|
- Approved PRs follow original budget
|
|
- New PRs use new budget allocation
|
|
|
|
---
|
|
|
|
## Next Steps in Procurement
|
|
|
|
### Immediately After Approval
|
|
|
|
#### 1. Procurement Review (Day 1-2)
|
|
- Procurement team reviews approved PR
|
|
- Verifies item specifications
|
|
- Confirms supplier availability
|
|
- Plans procurement method
|
|
|
|
#### 2. Sourcing Decision (Day 2-3)
|
|
Procurement decides:
|
|
- **Option A**: Create RFQ (multiple suppliers)
|
|
- **Option B**: Create PO directly (single supplier)
|
|
- **Option C**: Use framework agreement
|
|
|
|
#### 3. Document Creation (Day 3-5)
|
|
- RFQ or PO is created from PR
|
|
- PR status updates to "Converted"
|
|
- Procurement process continues
|
|
- PR serves as reference
|
|
|
|
### Timeline Expectations
|
|
|
|
#### Small Purchases (<$10,000)
|
|
```
|
|
Approval → PO Creation: 1-3 business days
|
|
PO Creation → Delivery: 5-10 business days
|
|
Total Time: 6-13 business days
|
|
```
|
|
|
|
#### Medium Purchases ($10,000-$50,000)
|
|
```
|
|
Approval → RFQ Creation: 2-3 business days
|
|
RFQ Process: 7-14 business days
|
|
PO Creation → Delivery: 10-20 business days
|
|
Total Time: 19-37 business days
|
|
```
|
|
|
|
#### Large Purchases (>$50,000)
|
|
```
|
|
Approval → RFQ Creation: 3-5 business days
|
|
RFQ Process: 14-30 business days
|
|
Evaluation & Award: 5-10 business days
|
|
PO Creation → Delivery: 20-45 business days
|
|
Total Time: 42-90 business days
|
|
```
|
|
|
|
*Note: Timelines vary by organization and procurement policy*
|
|
|
|
### Tracking Your PR
|
|
|
|
#### Status Monitoring
|
|
1. Navigate to **Procurement → Purchase Requisitions**
|
|
2. Find your PR by number
|
|
3. Check current status
|
|
4. View status history
|
|
|
|
#### Related Documents
|
|
Once converted, you can see:
|
|
- Link to RFQ (if created)
|
|
- Link to PO (if created)
|
|
- Related contracts
|
|
- Delivery documents
|
|
|
|
---
|
|
|
|
## Audit Trail
|
|
|
|
### What Is Recorded?
|
|
|
|
Every action on a PR is tracked:
|
|
|
|
#### 1. Creation
|
|
- Created by (user name)
|
|
- Created at (date/time)
|
|
- Initial values
|
|
|
|
#### 2. Modifications (Draft Stage)
|
|
- Changed by (user name)
|
|
- Changed at (date/time)
|
|
- What was changed (before/after values)
|
|
|
|
#### 3. Submission
|
|
- Submitted by
|
|
- Submitted at
|
|
- Status transition: Draft → Pending Approval
|
|
|
|
#### 4. Approval/Rejection
|
|
- Approved/Rejected by
|
|
- Approved/Rejected at
|
|
- Approval remarks
|
|
- User's IP address
|
|
- System information
|
|
|
|
#### 5. Modification Attempts (After Approval)
|
|
- Attempted by (user name)
|
|
- Attempted at (date/time)
|
|
- What user tried to change
|
|
- Why it was blocked
|
|
- IP address
|
|
- User agent
|
|
|
|
#### 6. Conversions
|
|
- Converted by
|
|
- Converted at
|
|
- Converted to (RFQ/PO)
|
|
- Reference numbers
|
|
|
|
### Viewing Audit Logs
|
|
|
|
#### For Regular Users:
|
|
- View approval history on PR detail page
|
|
- See who approved and when
|
|
- View approval remarks
|
|
|
|
#### For Administrators:
|
|
- Access full audit logs
|
|
- View all modification attempts
|
|
- See detailed change history
|
|
- Export audit reports
|
|
|
|
### Audit Log Retention
|
|
- **Standard Retention**: 7 years
|
|
- **Legal Requirements**: Per local regulations
|
|
- **Access Controls**: Restricted to authorized personnel
|
|
- **Backup**: Included in system backups
|
|
|
|
---
|
|
|
|
## Frequently Asked Questions
|
|
|
|
### General Questions
|
|
|
|
**Q: Can I edit my PR after approval?**
|
|
A: No. Once approved, PRs are permanently locked to maintain audit integrity and financial control.
|
|
|
|
**Q: What if I made a mistake in the PR?**
|
|
A: Contact your supervisor or procurement manager. Depending on the stage:
|
|
- Not yet converted: May need to create new PR
|
|
- Already converted: Changes must be in RFQ/PO
|
|
|
|
**Q: How long does approval take?**
|
|
A: Varies by organization. Typically 1-3 business days for standard PRs. Urgent PRs may be expedited.
|
|
|
|
**Q: Can I cancel an approved PR?**
|
|
A: Not directly. Contact procurement team. They can close it if not yet converted.
|
|
|
|
### Budget Questions
|
|
|
|
**Q: Does approval mean budget is spent?**
|
|
A: No. Budget is "committed" (reserved) but not spent until goods/services are received.
|
|
|
|
**Q: What happens if budget is unavailable?**
|
|
A: PR shouldn't be approved without budget. If approved incorrectly, finance will review.
|
|
|
|
**Q: Can I use the same budget for multiple PRs?**
|
|
A: Yes, as long as total doesn't exceed available budget. Each PR commits its portion.
|
|
|
|
### Process Questions
|
|
|
|
**Q: When will I receive my items?**
|
|
A: After approval:
|
|
1. PR converts to RFQ/PO (1-5 days)
|
|
2. Supplier processes order (varies)
|
|
3. Delivery (depends on items)
|
|
Total: 2-12 weeks typically
|
|
|
|
**Q: Can I track delivery?**
|
|
A: Yes, once converted to PO. PO will have tracking information.
|
|
|
|
**Q: What if supplier delays delivery?**
|
|
A: Contact procurement team. They manage supplier relationships and delivery schedules.
|
|
|
|
### Technical Questions
|
|
|
|
**Q: Why can't I click Save button?**
|
|
A: If PR is approved, there's no Save button. Document is locked. You can only view.
|
|
|
|
**Q: System shows "Document Locked" error**
|
|
A: This is normal for approved PRs. It's a security feature to prevent unauthorized changes.
|
|
|
|
**Q: Can admin override the lock?**
|
|
A: Generally no. Even administrators must follow audit and compliance rules. Special amendment procedures may exist.
|
|
|
|
---
|
|
|
|
## Important Reminders
|
|
|
|
### Before Submitting for Approval
|
|
|
|
✅ **Double-check everything** - You won't be able to edit after approval
|
|
|
|
✅ **Verify quantities** - Make sure amounts are correct
|
|
|
|
✅ **Confirm budget code** - Ensure correct budget is charged
|
|
|
|
✅ **Review pricing** - Verify prices are reasonable
|
|
|
|
✅ **Check delivery date** - Ensure timeline is realistic
|
|
|
|
### After Approval
|
|
|
|
📌 **Save your PR number** - Keep for tracking and reference
|
|
|
|
📌 **Monitor status** - Check periodically for updates
|
|
|
|
📌 **Coordinate with procurement** - They'll handle next steps
|
|
|
|
📌 **Plan for delivery** - Prepare for goods arrival
|
|
|
|
📌 **Keep documentation** - Save approval emails and documents
|
|
|
|
---
|
|
|
|
## Need Help?
|
|
|
|
### Quick Reference
|
|
|
|
- **View PR Status**: Procurement → Purchase Requisitions → Find PR
|
|
- **Check Budget**: Budget Reports or Finance Department
|
|
- **Track Delivery**: PO tracking once converted
|
|
- **Approval Issues**: Contact your supervisor
|
|
- **Technical Issues**: Contact IT Support
|
|
|
|
### Contact Information
|
|
|
|
- **Procurement Team**: [Your org contact]
|
|
- **Finance Department**: [Your org contact]
|
|
- **IT Support**: [Your org contact]
|
|
- **Supervisor**: [Department specific]
|
|
|
|
---
|
|
|
|
## Related Documentation
|
|
|
|
- **User Guide**: Complete guide to creating and approving PRs
|
|
- **FAQ Document**: Answers to common questions
|
|
- **System Administrator Guide**: Technical implementation details
|
|
- **Training Materials**: Available from IT Department
|
|
|
|
---
|
|
|
|
**Document End**
|
|
|
|
*This document explains the post-approval process. For complete PR lifecycle information, see the User Guide.*
|